Brief Report on Reconstruction of Tallah Bridge

Reconstruction of Tallah Bridge was conceived in October 2019 after conducting health study of the existing severely distressed bridge under the leadership of Dr. V.K. Raina. Dismantling of the existing bridge started in February 2020 and was completed in June 2020.

The bridge is located on BT Road near Tallah Water Tank and is a major important connectivity between Kolkata and North 24 Parganas.

The bridge comprises of 5nos of ROB Spans over 11nos of Railway tracks of Eastern Railway having 3nos spans of standard RDSO Bow String Girder and 2nos spans of Composite I-Girders and Viaducts of Shyambazar, Dunlop and Chitpur end along with approaches. Work order was issued to M/s Larsen & Toubro Limited with appointed date as 17.08.2020. Proof Consultant of this project is IIT-Chennai.

Authority's Engineer of this project is LASA-QSSIPL(JV).

External Technical Auditor & Independent Consultant of the project is IIT-Kharagpur. Some constraints were encountered in view of prevailing Covid situation and presence of numerous underground utilities including old KMC pipelines which needed to be jacketed. Total Administrative Approval of the project was 465.15Cr. Rs. 89.96 Cr. has been paid to Eastern Railway by the State Government for Utility Shifting, Inspection charges of RDSO, P&E and Supervision Charges (D&G), Way leave charges, Re-construction of 38nos of Railway Quarters and Construction of Temporary Level Crossing.

Salient Information
Name of Project Reconstruction of 4 Lane Tallah ROB (Hemanta Setu) Adjacent to Tallah Railway Station on Barrackpore Trunk Road, Kolkata, West Bengal on Engineering, Procurement, Construction (‘EPC’) basis
Administrative approval amount 465.11 Crores (INR)
Appointed Date 17th August 2020
Tendered amount 348.40 Crores (INR)
Authority Public Works Department, West Bengal
Authority’s Engineer LEA Associates South Asia Pvt.. Ltd. in Joint Venture with QSS Industrial Services Pvt. Ltd
EPC Contractor M/s Larsen & Toubro Limited,
Proof Consultant Indian Institute of Technology, Chennai
External Technical Auditor & IC Indian Institute of Technology, Kharagpur
Length of main bridge 743.43m
Length of Chitpur Ramp 296.86m
Carriage-way width of Main bridge 4 lane – 2 x 9.5 m each
Carriage-way width of Chitpur Ramp 2 lane – 1 x 8 m
Service road Total length - 1300 m for Shyambazar, Dunlop & Chitpur end
Footpath 1.5m wide footpath on either side of ROB proper
Technical Specification
Length of Main Bridge 743.43m
Length of ROB Proper 213.47m
Length of Chitpur Ramp 296.86m
Carriageway width 9.5m X 2 (From Shyambazar End to Paikpara End) 8.0m X 1 (Chitpur Ramp)
Width of footpath 1.5m (on Eastern & Western side of ROB proper)
Number of Piles 263nos of 1.2m/1m dia (Avg. Length 45m)
Number of Piers 22nos
Number of Abutments 3nos
Number of Approach structures 3nos
Number of Viaducts 15nos each 29.260m, 1no 29.242m, 1no 23.030m & 1no 12.534m (Composite I-Girder spans)
Number of Spans in ROB proper 5nos (3nos 52.080m each RDSO Standard welded Bow String girder spans, 1no 26.25m & 1no RDSO standard 30.98m Composite I-Girder spans)
Crash barrier Concrete crash barrier height varying from 850mm to 1550mm
Number of Railway tracks 11nos